By Muoki Charles
The affordable housing project in Thika town has given residents hope of owning a house in the busy town that is gearing to be elevated into a city in the coming years.
Launched in January this year near the Huduma Centre in the town, the project is 20 percent complete, with seven out of the expected 16 floors already done.
Works is still ongoing in the over 600 units in the four blocks as well as in other estates where the project is being implemented.
Speaking while on an inspection tour, Thika Member of Parliament (MP) Alice Ng’ang’a who was accompanied by the site engineer Miles Mwangi said from the progress noted, they expect the project to be complete by July next year.
The MP said more houses will be constructed in Starehe, Deport and UTI estates under the programme, as the town seeks to address its housing needs.
She said several people have already shown interest in the houses as they flock the site seeking information of how they can become beneficiaries.
“We were here five months ago when we laid the foundation of the project. Some people were doubting but now they have seen it’s a serious project. We are glad that there is serious progress. The houses are expected to go up to 16 floors and already, they are at seven. We hope by July, it will be handed over to the government,” Ng’ang’a said.
She added that other commercial buildings including supermarkets, playgrounds and other social amenities are set to be set up in the gated community.
On the economic impact of the project to residents, the MP said doors, windows and timber that is being used for the construction has been sourced from local carpenters and welders, thus improving livelihoods.
The legislator called on residents to take advantage of the project and own a house saying they are cheap, spacious and within the town.
“This is your time to own a house within the town. Register with Bomayetu and they will guide you. The demand for the houses is high and thus the need to register early,” All you need to do is to pay a 10% upfront,” she explained.
On his part, Eng. Mwangi while noting that they are on track to complete the project on time said the workmanship on the project has been exceptional.
He said the floods that hit the country in April and parts of May slowed the construction works, though they target to finish the infrastructure by February so as to focus on doing finish works and interior designs. – Kenya News Agency